You can set a number
of display and playback option for the Schematic view.
To access the Schematic options:
- With the cursor over the Schematic view,
middle-click or press the tilde (~) key and go through the south
gate.
- The settings for that Schematic view
are displayed.
NoteIf more than one
Schematic view is open, your cursor must be placed over the Schematic
view on which you want to set options.
To set the display options:
- Select the display tab.
- Then set the display options.
Select: |
To: |
Navigator |
Show or hide the Schematic Navigator. By default, the Navigator
is displayed.
|
Highlights |
Expand and highlight the tabs of a node when you pass
the cursor over them.
|
Links |
Change the line style of connections. Lines can appear
as: Curved, Straight, or Angled.
|
- Finally, set the placement options.
Select: |
To: |
Auto Layout |
Automatically organize all of the nodes in the dependency graph. |
Auto Zoom |
Automatically zoom to keep the complete dependency graph visible
in the center of the Schematic view.
|
Locate Node |
Automatically locates a specific node in the Schematic
when you select in the Composition browser.
|
NoteYou can make any
of the display settings the default settings for the view by selecting
them in your user preferences. See
Setting User Preferences.
To hide the Schematic Navigator in the
full screen Schematic:
- Middle-click or press the tilde (~) key
to display the drop gate, and swipe north to view the full screen
Schematic.
- Middle-click or press the tilde (~) key
to display the drop gate, and swipe south to the Schematic Options.
- Under Display, select Navigator to hide
the Navigator. By default, the Navigator is visible.
To set the playback options:
- Select the Playback tab.
- Then set the ViewerTime options:
Set: |
To: |
Follow Master |
Sets the view to global time. Disable to use its own
global time.
|
Offset |
Lets you set a frame offset for the time. The frame offset
is with respect to the time you set for the view. For example, if
you set a frame offset of 5 and selected the Follow Master option,
the proxy in the view always displays the frame that is five frames ahead
of the frame currently running in global time. If you deselected
Follow Master, the proxy in the view always displays the frame that
is five frames ahead of the frame running in the local time of the
view.
|
Update on Play |
Updates the proxy at each frame when you play the composition.
Deselect to update proxy only when you stop playing the composition,
and only at the scrub frames when you scrub through the composition.
|
- Finally, set the Frame Rate options:
Set: |
To: |
Play All Frames |
Plays all frames in the composition, regardless of whether
it maintains the frame rate set for the composition. Deselect to have
the view maintain the frame rate for the composition, at the expense
of dropping the frames where necessary.
|
User |
Lets you set the frame rate at which you want the Schematic view
to play the composition. Type the frame rate in the field to the
right of this button, or click and drag the bottom edge of the field
to adjust the value.
|
Stop on Drop |
Stops the Player if a tool is dropped into the dependency
graph
|
Things to Remember:
- Each Schematic view has its own set of
options except for the flow (left-right, top-bottom, etc.)